How Long a Louvered Pergola Takes to Install

How Long a Louvered Pergola Takes to Install

Installation time is the question every contractor asks before signing, and the honest answer depends on three things: whether the bases are ready, how many bays there are, and whether the frame arrives in sets. A single freestanding bay on prepared bases is a day’s work for two people. A four-bay roof with motors, screens and glass doors is a week for three, and most of that week is not the frame.

The parts of the job that take time

  • Setting out and bases. Measuring the diagonals, marking the pads, drilling and anchoring. On a paved terrace this is the slowest part, because a pad has to be formed below the paving.
  • Posts and beams. Two people can lift a 4 metre beam; a 6.5 metre beam on the heavy-duty class needs three or a small lifting aid.
  • Blades and the drive. Blades go in as a group with the link bar; the motor, the limit settings and the control position take an hour or two per bay and cannot be rushed.
  • Drainage. The water outlet, the downpipe route and the fall. If the fall is built into the frame correctly this is quick; if the site fall was misread it is a rebuild.
  • Extras. Glass sliding doors, zip screens, LED strips. Each has its own alignment and its own tolerance.

Two people, three people, or a lift

Our span classes set the site requirement. The manual class with 160 by 29 blades and 140 by 100 beams is a two-person frame on a single bay. The standard class is comfortable for two on the frame and three on the beams. The heavy-duty class with 220 by 142 beams and 160 by 160 posts is a three-person frame for any bay over 5 metres, and a bay over 6 metres is easier with a lift or a scaffold tower than with four people on ladders.

Add one person whose only job is to hold the tape and check the level. It is the cheapest labour on the site.

What a one-day install looks like

A single bay, prepared bases, no extras: arrive at eight, set out and check diagonals by half past, plates and posts by ten, beams by eleven, blades by one, limits and control by two, hose test by three, and the frame is done with time to clear the site. Two people can hold that pace on the manual class. On the standard class the same day works if a third person handles the beams and the level.

Two bays of the same class is not two days: the second bay shares the setting out and the frame logic, so it is usually a day and a half rather than two. The extras are what break the pattern, which is why they are quoted separately and scheduled separately.

What adds a day, and what adds a week

A day: a bay that has to be re-set because the diagonals were checked after the anchors went in. A motor whose control cable was not routed before the frame closed up. A wall plate that needed a spreader nobody brought.

A week: bases that are not poured, because the crew arrives and stands down. A custom colour that arrives with one bay in a different batch. Glass that was ordered against the frame dimensions before the frame was set and is 8 mm out. All three are decisions made before the crate is opened.

The sequence that keeps a crew moving

Bases first and cured. Posts and levelled. Beams on. Blades in groups, from one end. Drive and limits. Drainage tested with a hose before the roof is closed. Then the extras, in the order they were designed to fit: screens before glass in most cases, because the screen cassette sits behind the door track.

Test the water before the last panel goes on. A leak found with the roof open costs an hour; the same leak found after the glass is in costs a day.

Staffing on a multi-bay roof

Four bays is where the pace changes. Two people carry the frame, one sets limits and one keeps the level, and swapping those roles mid-job wastes the advantage. Assign them at the start: a fitter on the frame, a fitter on the blades, and a third person on measurement and water testing. The third person is the one who catches the bay that is 15 mm out before the anchors are torqued.

What the factory can do to shorten the site work

Three things, and all of them are drawing decisions. Mark every profile with the bay and the elevation so the crate is opened in the right order. Pre-assemble the blade groups with the link bar so the site joins groups rather than individual blades. Ship the base plates with the anchor set matched to the substrate, rather than a generic box of bolts.

Ask for those three at the quotation stage. They cost almost nothing in the factory and they remove most of the standing-around time on site.