What the Installer Needs on Site Before the Crate Is Opened
The crate arrives, the site is ready, and the crew discovers that the anchor bolts are in the box but the drill bit is not, or that the wall is 40 mm thicker than the plate detail assumes. Half a day goes. Most of what stops an installation is known before the crate is opened, and the list is short enough to check the day before.
The site, before the crate is touched
- Base pads finished and cured. Not poured that morning. Anchors in green concrete pull out.
- Ground cleared along the full length of the longest beam, plus a metre either side. A 6.5 metre beam needs 6.5 metres of clear approach.
- Access for the delivery. Where the truck stops, how far the crate has to travel, and whether a pallet truck can reach the unloading point.
- Power at the terrace if the roof is motorised, with an isolator that can be reached.
- The wall exposed where the plate will land: finish removed, thickness known.
The tools that are actually needed
A rotary hammer with the right bit for the anchor type, a torque wrench, two tapes (one long enough for the diagonal), a spirit level and a straight edge or laser, a string line, a hacksaw or a multi-tool for trimming, a hose for the water test, and a set of Allen keys that match the fixings. Add a small generator if there is no power on site, and a covered extension lead that can reach the far end of the roof.
The one tool crews forget is a second ladder or a scaffold tower for a beam over 5 metres. Two ladders and four people is slower and less safe than one tower and two.
What to open first, and why
Open the crate that carries the packing list first, and read the list against the marks. Marks should name the bay and the set; if they do not, the crate order is a guess and the site stops while somebody finds out. Then open the bay that the drawing puts first, which is normally the one with the wall plate or the lowest numbered bay.
Keep the factory wrapping on every profile until it is in position. Wrapping is the cheapest protection available and it is thrown away too early on most sites.
The materials that should be on site before the frame
Anchor bolts matched to the substrate, a tube of the specified sealant, touch-up paint in the frame colour, and spare paver if the paving is being lifted. Four items, all cheap, and each one of them stops a job when it is missing.
The brief the installer should have in writing
Which bay goes where, the post heights, the outlet position, the control position, and whether the screens go in before or behind the door track. One page, drawn from the shop drawing. A crew that has to interpret a 40-page drawing set on site will interpret it differently from the factory.
Our own handover note travels with every set: marks, bay order, and the two checks that must be done before the last panel goes on. Ask for it if it is not in the crate.
What the crate order tells you
Crates should be packed in the order the bays are installed, with the wall plate bay first on a wall-mounted roof. If the first crate holds the seats and the screens instead of the posts and the beam, the crew works around the boxes all day. Ask for the packing sequence when the order is confirmed, and check it against the packing list before the container is stripped.
Bundles inside a crate should be banded by bay and labelled on the outside of the band, not on a label that falls off in transit. A bundle that has to be unwrapped to be identified has already cost the site half an hour.
The day-before checklist
- Pads cured, marked and photographed; the marked centres match the drawing.
- Access route clear for the longest beam and for the crate.
- Power available and an isolator reachable, if motorised.
- Drill, bits, torque wrench and long tape on site, not in a van two hours away.
- Wall exposed where the plate lands, and the wall construction confirmed against the detail.
- Packing list to hand, and the person who will sign for the crates identified.
- Weather window: blades on a windy day is the job that gets somebody hurt.
Seven items, an hour of checking, and most of the lost days on a first installation disappear.
If something is missing
Photograph the packing list, the crate marks and the empty slot, and send all three in one message. A missing profile is a factory question, and the factory can only answer quickly with a photograph and a list. One photo with the list is worth ten emails describing a bolt.
Related: nine marks to check when your container arrives.
Next step: the three series and their specifications are on the louvered pergola product page. If you already have bay sizes, send them through the contact form for a first price.
Keep reading

Setting Out a Bay: Square, Level and Fall in One Pass
Setting out a pergola bay: check square with diagonals, level posts from one datum, build the fall in…
Read article →
Installation Sequence for a Louvered Pergola
Installation sequence for a louvered pergola: set out, plates and posts, beams and wall plate, blades, drive limits,…
Read article →
Anchoring a Pergola into Existing Paving Without Breaking It
Anchoring a pergola into finished paving: pads below the paving, plate and spreader, or ballasted feet, plus what…
Read article →Related notes
- Setting Out a Bay: Square, Level and Fall in One Pass
- Anchoring a Pergola into Existing Paving Without Breaking It
- Installation Sequence for a Louvered Pergola
Working on a project? Send a drawing and we reply from the Foshan plant with a first price. Not sure which line fits — start from the six product lines.