Setting Out a Bay: Square, Level and Fall in One Pass
Setting out is the step where a good pergola becomes a bad one, and it takes an hour. Three properties have to be true at the same time: the bay is square, the posts are level with each other, and the roof has a fall towards the outlet. Check them in that order, because a bay that is out of square cannot be made level, and a fall built into a frame that is twisted will not read on a level.
Square first: the diagonals, not the sides
Measure both sides and both ends, and then measure both diagonals. On a true rectangle the diagonals are equal. On a bay where one side is 20 mm long, the diagonals differ by roughly the same amount, and the frame will fight itself when the blades go in. If the diagonals differ, move a post — never force the frame.
The 3-4-5 method does the same job from one corner: 3 metres along one edge, 4 along the other, and the diagonal between those marks should read 5. Multiply everything by two on a large bay for a longer, more accurate measurement. A 6 metre bay measured with a 3 metre triangle is less reliable than a 6-8-10 triangle measured to the same marks.
Level: posts against each other, not against the ground
Posts are levelled to each other, using a laser or a long straight edge with a spirit level, not individually to the ground. Ground that looks flat rarely is: a paved terrace typically falls 1 to 2 per cent for drainage, and levelling each post to its own patch of ground produces a frame that is level in four different directions.
Set a datum once — a mark on a wall, a bench mark on a post — and measure every post from it. Then check the tops with a straight edge laid across two posts at a time.
Fall: the third property, and the one most often lost
A louvered roof drains to an outlet at one end, so the roof needs a fall of its own: typically a small percentage along the beam towards the outlet, built into the frame rather than into the blades. If the frame is set dead level, water sits on a closed blade until it finds the seam, and the leak is blamed on the seal rather than on the fall.
Build the fall in at the post stage, because correcting it afterwards means re-setting plates. On a wall-mounted bay the wall plate sets the high end and the posts are set to match it, which is why the plate is fixed before the posts are trimmed.
Marking, so the crew does not re-measure
Mark the pad centres, not the plate edges. A plate can be shifted a few millimetres and still cover its pad; a pad that is in the wrong place cannot be shifted at all. Spray a cross at each centre and write the bay number next to it, then photograph the marked ground before drilling. On a multi-bay roof those photographs are the only record of what was marked and where.
The instruments that are good enough
A 5 metre tape is not enough on a 6.5 metre bay, because the tape sags and the last 500 mm reads short. Use a tape long enough for the diagonal, or a laser measure. A rotating laser is the fastest way to set a datum across four posts; a 1.2 metre spirit level and a straight edge do the same job more slowly. A string line confirms what the instruments say, and it catches the post that has moved since it was measured.
Multi-bay roofs: bay by bay, from one datum
On a four-bay roof the error compounds. Set the first bay against the wall plate, then set the second bay from the first — not from the wall again — and check the diagonals of each bay separately rather than only the outer rectangle. A run of bays that is square overall but has one twisted bay in the middle will show as a blade group that binds, and the fix is at the plates rather than at the blades.
Keep a single datum for the whole run, and number the posts on the ground before drilling. A bay that has been set out from two different datums is a bay that will be out by the difference between them, and the difference is usually the tape.
What to do when the site will not cooperate
Sites that are out of square by more than the frame can absorb, or grounds that fall the wrong way, are not solved by forcing the frame. Two options exist: change the base detail so the posts can be trimmed or extended, or change the bay so the frame follows the site. Both are drawing changes and both are cheap before cutting. On site, ten millimetres is a discussion; in the factory, it is a number on a drawing.
Related: setting posts plumb.
Next step: the three series and their specifications are on the louvered pergola product page. If you already have bay sizes, send them through the contact form for a first price.
Keep reading

What the Installer Needs on Site Before the Crate Is Opened
What an installer needs before the crate is opened: pads cured, access clear, the right drill and anchor…
Read article →
Installation Sequence for a Louvered Pergola
Installation sequence for a louvered pergola: set out, plates and posts, beams and wall plate, blades, drive limits,…
Read article →
Anchoring a Pergola into Existing Paving Without Breaking It
Anchoring a pergola into finished paving: pads below the paving, plate and spreader, or ballasted feet, plus what…
Read article →Related notes
- Anchoring a Pergola into Existing Paving Without Breaking It
- Installation Sequence for a Louvered Pergola
- How Long a Louvered Pergola Takes to Install
Working on a project? Send a drawing and we reply from the Foshan plant with a first price. Not sure which line fits — start from the six product lines.